  1. Question 1

    CDS 2 2017

    37
    30 men can complete a job in 40 days. However, after 24 days some men out of the assigned 30 left the job. The remaining people took another 40 days to complete the job. The number of men who left the job is

    Tap an option to check your answer.

  2. Question 2

    CDS 1 2024

    29
    50 men can complete a work in 40 days. They begin the work together but a batch of 5 men left after each period of 10 days. What is the time to complete the work ?

    Tap an option to check your answer.