Men-days stay constant: workforce or food lasts when the number changes
This type of question, asked 4 times: 27 Jun 2024 S3, 29 Jun 2024 S2, 12 Dec 2025 S1, 12 Dec 2025 S2. All 5 questions below, oldest first.
Try each one first, then open its answer.
Question 1
27 Jun 2024 S3
12518 workers can complete a piece of work in 96 days. They start working together and after 26 days 10 more workers join them. In how many days in all will the work be completed?Tap an option to check your answer.
Question 2
27 Jun 2024 S3
117If 24 people can build 90 identical walls in 25 days, then how many more days will 27 people require to build 162 such walls?Tap an option to check your answer.
Question 3
29 Jun 2024 S2
135A hostel had food provision for 300 students for a month. After 20 days, 50 students left the hostel. How long would the remaining food last? (1 month = 30 days)Tap an option to check your answer.
Question 4
12 Dec 2025 S1
111A small construction firm has 6 workers who can complete a road patching job in 8 days. If 4 more workers are added, how many days will they take to finish the same work?Tap an option to check your answer.
Question 5
12 Dec 2025 S2
112A job can be done by 18 women in 10 days. After working for 4 days, 6 women leave. How many more days will the remaining women take to finish the job?Tap an option to check your answer.