CDS Mathematics · Time and Work
Man-Days and Man-Hours
A fixed job needs a fixed number of man-days (or man-hours), so men × days × hours stays constant for the same work.
Why this matters
Seventeen PYQs, none HARD. Extra men to finish on time, men who leave half-way, a bigger wall, 20 persons and 20 floors: measure the job in man-days once, then share out what is left. Five more hide the same idea inside algebra, 'work of (x + 2) men in (x − 3) days'.
Concept 1 of 1: Men × days × hours
Definition
- .
- Part done, part left: total man-days man-days used fraction done; the rest is shared over the days left.
- Men leaving in batches: add the man-days block by block until the job is covered.
- Work measured by size (a wall's volume, rooms, hectares): the work is proportional to it.
Constant work
Worked example
Practice this conceptself-check · 4 quick reps
The same idea in a real exam question:
Example 1 · Time and Work · Man-Days and Man-Hours
Count the whole job, not the part
Additional men, or men in all?
Summary — formulas & gotchas at a glance
A revision cheat-sheet for the formulas and gotchas above. Click any concept name to jump back to its full explanation.
Formulas (1)
- Men × days × hours
Constant work
Watch out for (2)
- Count the whole job, not the part→ Men × days × hours
- Additional men, or men in all?→ Men × days × hours