Concept 1 of 5: Man-days: workers × days
Definition
- Work = workers × days. For the same job, .
- More workers means fewer days. Halving the team doubles the time.
- If only part of the job is done, scale the man-days: of a job in 300 man-days means the whole job is 500 man-days.
- Anything used at a steady rate works the same way: food eaten, pages typed.
Man-days
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a practice question:
Example 1 · Time and Work · Man-Days and Group Work
More workers, fewer days
Concept 2 of 5: Man-hours: when the working day changes
Definition
- Work = men × hours a day × days. For the same job, .
- The unknown can be any one of the three: men, hours a day or days.
- Weeks work the same way: men × days a week × hours a day × weeks.
Man-hours
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a practice question:
Example 2 · Time and Work · Man-Days and Group Work
Hours a day are part of the work
Concept 3 of 5: When the amount of work changes
Definition
- , where is the output: walls, metres, chairs, books.
- Labour for one unit of output is . Leave out when hours are not mentioned.
- An unknown output is the labour available ÷ the labour per unit.
- Phases of a job split in a ratio: the labour for each phase is in that ratio.
Work with output
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a practice question:
Example 3 · Time and Work · Man-Days and Group Work
Output goes under the labour
Concept 4 of 5: Converting men, women and children
Definition
- ' men or women' in the same time means men = women, so 1 man = women.
- Convert the new team into women (or men). The job is then women × days.
- Three kinds at once, such as '1 man or 2 women or 4 children': convert everyone to children, or give each a rate and add.
- Half of one team plus half of the other makes one full team, which takes the same time.
Equivalent workers
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a real exam question:
Example 4 · Time and Work · Man-Days and Group Work
'Or' is not 'and'
Concept 5 of 5: Two mixed teams: solve for one worker
Definition
- Same job: (team 1's daily work) × its days = (team 2's daily work) × its days.
- That gives the ratio , and the job becomes a number of woman-days.
- If the two teams take the same time, their daily work is equal.
- From 'x men take a days and y women take b days', the efficiency ratio is .
Equal work
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a practice question:
Example 5 · Time and Work · Man-Days and Group Work
Equal work, not equal daily work
Summary — formulas & gotchas at a glance
A revision cheat-sheet for the formulas and gotchas above. Click any concept name to jump back to its full explanation.
Formulas (5)
- Man-days: workers × days
Man-days
- Man-hours: when the working day changes
Man-hours
- When the amount of work changes
Work with output
- Converting men, women and children
Equivalent workers
- Two mixed teams: solve for one worker
Equal work
Watch out for (5)
- More workers, fewer days→ Man-days: workers × days
- Hours a day are part of the work→ Man-hours: when the working day changes
- Output goes under the labour→ When the amount of work changes
- 'Or' is not 'and'→ Converting men, women and children
- Equal work, not equal daily work→ Two mixed teams: solve for one worker