AFCAT Numerical Ability · Time and Work
When Workers Leave or Join Mid-Job
Take the man-days already done away from the job, give what is left to the team now on site, and compare with the plan only when the question asks.
Why this matters
No AFCAT past-year question is on this page yet, but it is the second largest in the chapter and most of it is MODERATE. The method is one line; the marks go on the question's last words, because 'more days', 'days in all' and 'days beyond the plan' are three different answers.
Concept 1 of 4: Work left after the team changes
Definition
- Work left = job minus (old team × days worked).
- More days = work left ÷ new team. Days in all = days already worked + more days.
- Several changes: take away each stage's man-days in turn.
- A change by a fraction, such as 'a third of them leave': call the team 3 parts, so 2 parts stay.
Days after a change
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a practice question:
Example 1 · Time and Work · Workforce Changes Mid-Job
Take away the work already done
Concept 2 of 4: Extra days against the plan
Definition
- Planned days left = planned total minus days worked.
- Extra days = actual days left minus planned days left. If workers join, the same difference is the days saved.
- Shortcut when workers leave a team of with planned days left: extra days = .
- Read the last words. 'Extra', 'beyond the plan' and 'after the planned date' ask for the difference; 'more days to finish' asks for the actual days left. 'Additional days' is used both ways, so check which reading is among the options.
Extra days
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a practice question:
Example 2 · Time and Work · Workforce Changes Mid-Job
Extra is not the same as more
Joining saves days
Concept 3 of 4: Keeping to the deadline
Definition
- Workers needed = work left ÷ days left. Hire the difference between that and the workers still on the job.
- Hours a day needed = man-hours left ÷ (workers × days left).
- 'Will it finish on time?': work out the days the new team needs and compare them with the days left in the plan.
Team needed
Worked example
Practice this conceptself-check · 2 quick reps
The same idea in a practice question:
Example 3 · Time and Work · Workforce Changes Mid-Job
Count from the workers still there
Concept 4 of 4: Hours, efficiency and team size change together
Definition
- When hours a day change, count the work in man-hours: men × hours × days.
- New workers at efficiency count as of a worker each. Overtime that raises efficiency by 25% makes each worker count as 1.25.
- Unknown team size: write the job as × planned days, write it again from the story that happened, and solve for .
- A fixed end date with stages: the last group works whatever is left of the schedule.
Standard workers
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a practice question:
Example 4 · Time and Work · Workforce Changes Mid-Job
Efficiency changes the team, not the job
Each stage at its own hours
Summary — formulas & gotchas at a glance
A revision cheat-sheet for the formulas and gotchas above. Click any concept name to jump back to its full explanation.
Formulas (4)
- Work left after the team changes
Days after a change
- Extra days against the plan
Extra days
- Keeping to the deadline
Team needed
- Hours, efficiency and team size change together
Standard workers
Watch out for (6)
- Take away the work already done→ Work left after the team changes
- Extra is not the same as more→ Extra days against the plan
- Joining saves days→ Extra days against the plan
- Count from the workers still there→ Keeping to the deadline
- Efficiency changes the team, not the job→ Hours, efficiency and team size change together
- Each stage at its own hours→ Hours, efficiency and team size change together
Drill the questions on this topic
75 questions from the bank, with cart and Word export.