SSC CGL Maths · Time and Work
Working on Alternate Days
When workers take turns, find the work done in one full cycle of turns, count how many whole cycles fit, then finish the last part one day at a time.
Why this matters
Nineteen questions in the bank, sixteen of them MODERATE and one HARD: two people on alternate days, three in rotation, or helpers who join every second, third or fifth day. Nearly every wrong option comes from the last cycle, so this page always finishes it one day at a time.
Concept 1 of 2: Taking turns on alternate days
Definition
- Take the job as LCM units. One cycle does the sum of the turn-takers' daily units.
- Whole cycles: take as many as fit while some work is still left after them. Then go day by day in the same order. The last day may be a part day: units left that worker's daily units.
- Who starts matters when the job ends inside a cycle. With the faster worker first, it can end sooner.
- The job is a whole number of cycles: the answer is cycles cycle length, but check the first worker of the last cycle cannot already finish it.
- Three people in rotation: the cycle is 3 days, and the same steps apply.
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a real exam question:
Example 1 · Time and Work · Working on Alternate Days
Rounding a part day up to a whole day
Ignoring who starts
Taking one cycle too many
Concept 2 of 2: Helpers who join every few days
Definition
- Helpers every -th day: one block is days. Its work the regular worker's days the helpers' work on their day.
- Fill whole blocks, then go day by day. The helpers' day is the LAST day of each block, so in a part block at the end they may not appear at all.
- Days off: a worker who rests after every 4 days of work rests on days 5, 10, 15 and so on. By day he has worked days ( means with its fraction dropped).
- One works daily, two alternate: if R works every day while S and T take turns, the cycle is 2 days: R and T, then R and S.
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a real exam question:
Example 2 · Time and Work · Working on Alternate Days
Putting the helpers' day first
Reading a day off after every 4 days as a 4-day rhythm
Summary — formulas & gotchas at a glance
A revision cheat-sheet for the formulas and gotchas above. Click any concept name to jump back to its full explanation.
Watch out for (5)
- Rounding a part day up to a whole day→ Taking turns on alternate days
- Ignoring who starts→ Taking turns on alternate days
- Taking one cycle too many→ Taking turns on alternate days
- Putting the helpers' day first→ Helpers who join every few days
- Reading a day off after every 4 days as a 4-day rhythm→ Helpers who join every few days
Test yourself on Time and Work
20 past SSC CGL questions from this chapter, timed at 12 minutes and marked the way the exam marks it. You see your score and every answer the moment you finish. Free to start.