When people work for different stretches of time, add each stretch's work (rate times days) and set the total equal to one whole job.
Why this matters
Twenty-one questions in the bank, thirteen MODERATE and one HARD, eight of them from the 2025 shifts: one worker hands over to another, a helper joins, someone leaves after a few days or a few days before the end. The method never changes: one line for each stretch, then add the lines.
Concept 1 of 3: One worker starts and another finishes
Definition
- Work in a stretch daily rate of whoever is working days of that stretch.
- All stretches add to 1 (or to the whole job in LCM units).
- An unknown rate: if A works first and does of the job, the rest, , took B the stated days. So B's rate the rest B's days, and B's time for the whole job follows.
- Regroup, fast route: if A works days and B works days () and you know how long A and B take together, write . The pair part is known, so B comes out in one step.
Work in stretches
- one-day rates of the two workers
- p, qdays each of them works
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a real exam question:
Example 1 · Time and Work · Workers Joining and Leaving
Taking the days for the rest as the whole time
Concept 2 of 3: A team that changes partway
Definition
- Stretch 1: team rate days. Stretch 2: new team rate days. The two add to 1.
- When did A leave? If A left after days and B alone finished in days, . Fast route: take B's days of work off first; what is left was done by the pair at the pair's rate.
- A joiner's rate: work left after stretch 1 days of stretch 2 gives the new team's rate; take away the members you know.
- Efficiencies given: use them as units a day, with the whole job one worker's efficiency that worker's days.
- Pay still follows work done: add up each person's work across both stretches.
- Read what is asked: only the days after the change, or the total from the start.
Team changes partway
- xdays the full team works
- ddays the smaller team works after the change
- one-day rates
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a real exam question:
Example 2 · Time and Work · Workers Joining and Leaving
Giving the days after the change when the total is asked
Forgetting the old members in a joiner's rate
Concept 3 of 3: Leaving a few days before the end
Definition
- Let the job take days. A worker who leaves days before the end works days; one who stays works all .
- Write and solve for .
- LCM units, fast route: with whole-number rates, (all the rates added) minus each leaver's rate the days they missed equals the job's units.
Leaving k days before the end
- Ttotal days the job takes
- one-day rate of worker i
- days before the end that worker i leaves (0 if they stay)
Worked example
Practice this conceptself-check · 2 quick reps
The same idea in a real exam question:
Example 3 · Time and Work · Workers Joining and Leaving
Taking the leaving days off the leaver's own time
Summary — formulas & gotchas at a glance
A revision cheat-sheet for the formulas and gotchas above. Click any concept name to jump back to its full explanation.
Formulas (3)
- One worker starts and another finishes
Work in stretches
- A team that changes partway
Team changes partway
- Leaving a few days before the end
Leaving k days before the end
Watch out for (4)
- Taking the days for the rest as the whole time→ One worker starts and another finishes
- Giving the days after the change when the total is asked→ A team that changes partway
- Forgetting the old members in a joiner's rate→ A team that changes partway
- Taking the leaving days off the leaver's own time→ Leaving a few days before the end