SSC CGL Maths · Time and Work
Man-Days and Man-Hours
A job needs a fixed amount of labour, counted as workers times days (times hours a day), so more workers finish sooner in exact proportion.
Why this matters
Nineteen questions in the bank, eleven EASY and eight MODERATE, five of them from the 2025 shifts: more men for an earlier deadline, a change in hours a day, men added partway, or a few men leaving every day. Every one rests on a single product, workers × days × hours, which stays the same for the same work.
Concept 1 of 3: Workers times days is fixed for a job
Definition
- Man-days of a job workers days. It is the same for any team of equally able workers.
- Fewer days need more workers: workers needed man-days days.
- A different amount of work: man-days scale with the work. Twice the work needs twice the man-days; a fraction of the job needs of them.
- The full rule: .
- "How many more" workers workers needed workers already there.
Man-days rule
- numbers of workers
- days taken
- amounts of work (1 for the whole job)
Worked example
Practice this conceptself-check · 4 quick reps
The same idea in a real exam question:
Example 1 · Time and Work · Man-Days and Man-Hours
Working the proportion the wrong way
Giving the total when "how many more" is asked
Concept 2 of 3: Hours a day and part of a job
Definition
- Man-hours workers days hours a day.
- The rule: . Put the part of the job each team does (40%, the remaining 60%) in .
- One worker's hours: if A needs 5 hours a day for 8 days, the job takes A 40 hours in all. For two workers, add their hourly rates, then divide the total hours by the hours worked each day.
- Efficiency and hours together: units done a day efficiency per hour hours a day.
Man-hours rule
- numbers of workers
- days worked
- hours worked each day
- parts of the job done
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a real exam question:
Example 2 · Time and Work · Man-Days and Man-Hours
Ignoring a change in hours a day
Putting the part of the job on the wrong side
Concept 3 of 3: Workers added or leaving partway
Definition
- Man-days left total man-days workers days already worked.
- Days for the rest man-days left the new number of workers. If the hours a day change too, use man-hours.
- A fixed number leave every day: the workers present form a sequence . Over days they put in man-days. Set that equal to the planned man-days.
- Fast route for the sequence: total number of days the average of the first and last day's workers.
Changing workforce
- nworkers at the start
- Ddays the job would take them
- tdays already worked
- n'workers after the change
- kworkers who leave at the end of each day
- ddays the job actually takes
Worked example
Practice this conceptself-check · 3 quick reps
The same idea in a real exam question:
Example 3 · Time and Work · Man-Days and Man-Hours
Starting the leaving sequence one day early
Summary — formulas & gotchas at a glance
A revision cheat-sheet for the formulas and gotchas above. Click any concept name to jump back to its full explanation.
Formulas (3)
- Workers times days is fixed for a job
Man-days rule
- Hours a day and part of a job
Man-hours rule
- Workers added or leaving partway
Changing workforce
Watch out for (5)
- Working the proportion the wrong way→ Workers times days is fixed for a job
- Giving the total when "how many more" is asked→ Workers times days is fixed for a job
- Ignoring a change in hours a day→ Hours a day and part of a job
- Putting the part of the job on the wrong side→ Hours a day and part of a job
- Starting the leaving sequence one day early→ Workers added or leaving partway